Murata Announced Completion of New MLCC Production Building

Izumo Murata Manufacturing Co., Ltd., a manufacturing subsidiary of Murata Manufacturing Co., Ltd. located in Izumo City, Shimane Prefecture, has completed construction of a new MLCC production building at its Iwami Plant in Hane that had been under construction since March 2022.

The completion ceremony was held on Thursday, April 27, 2023. With the completion of the new production building, Murata will establish a system that can respond to the medium- to long-term increase in demand for MLCC multilayer ceramic capacitors.

Overview of the new production building at the Iwami Plant (Hane)

Structure and scale:Steel-frame construction, four stories above ground 
Total floor area:22,144 ㎡
Building area:6,314 ㎡
Purpose:Production of multilayer ceramic capacitors
Completion date:Monday, April 24, 2023
Total investment:Approx. 12 billion yen (including buildings and manufacturing equipment)